Highland Avenue Resurfacing Project (Princeton to Villa)

General Information

Project Location(s):
Highland Avenue from Princeton to Villa
Project Status:
Contract Execution
Bid Opening Date:
Thursday, August 18, 2025, at 10:00 a.m. CST
Mandatory Pre Bid Meeting:
No
QuestCDN Number:
9807376
Construction Start Date:
2025
Construction Completion Date:2025
Contractor:
Builders Paving, LLC
Construction Engineer:
V3 Companies, Inc.
Design Engineer:
TranSystems Corporation
Awarded Contract Amount:
$510,885.00
Adjusted Final Contract Amount:
TBD
Funding Source(s):
MFT Funding

Objective

To improve the condition of the roadway by means of selected pavement rehabilitation methods.

Description

This project consists of milling and resurfacing, intermittent curb and gutter removal and replacement, driveway removal and replacement, ADA ramps with detectable warnings, pavement patching as needed, drainage and utility structure adjustments or reconstructions with new frame and lid/grate, and landscaping.

Justification

The Village’s Pavement Management Program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed.

Bidding & Planholders Information

Bidding will be conducted online through the bidding service QuestCDN.

Project Updates

Date
Description
October 10, 2025Construction is underway. Curb and sidewalk work is being performed, with asphalt resurfacing to follow in the coming weeks.
September 19, 2025A notice was delivered to residents within the project area, informing them of the upcoming construction. A pre-construction meeting with the contractor is scheduled for Friday, September 26, 2025.
August 29, 2025A bid opening was held this week. The bids are currently under review.
August 14, 2025The project has been advertised for bidding. The bid opening is scheduled for Thursday, August 28, 2025, at 10:00 a.m., via Microsoft Teams.
April 4, 2025Design of the project is underway.