2024 Pavement Markings Program

General Information

Project Location(s):
Various
Project Status:
Contract Execution
Bid Opening Date:N/A
Mandatory Pre Bid Meeting:
N/A
QuestCDN Number:
9221610
Construction Start Date:
October 7, 2024
Construction Completion Date:
Fall 2024
Contractor:
Superior Road Striping
Construction Engineer:In-House
Design Engineer:
In-House
Awarded Contract Amount:
$85,461.25
Adjusted Final Contract Amount:
TBD
Funding Source(s):
Street Maintenance Fund

Objective

To remove worn down roadway pavement markings and replace them with fresh, IDOT standard replacement markings.

Description

This project consists of the removal of worn pavement markings and their replacement with fresh markings at various locations within the village.

Justification

The identified pavement markings have deteriorated to the point where replacement is needed.

Project Updates

Date
Description
January 10, 2025The remainder of the work is on hold until weather conditions improve. The remaining work is expected to be completed in the spring.
October 11, 2024Contractual maintenance of pavement markings on asphalt streets began late this week and is expected to be completed by the end of next week, weather permitting. Maintenance of pavement markings on concrete streets, which utilizes a different material and is performed by a different crew, is expected to take place later this year.
October 4, 2024Work is expected to begin next week.
September 13, 2024A contract with Superior Road Striping, Inc. was approved at this week's Village Board meeting.
August 30, 2024Design of the project is complete.
January 1, 2024This project is in the planning stages.