Wisconsin Avenue Improvement Project (Vermont to Ridge)

General Information

Project Location(s):
Wisconsin Avenue (Vermont to Ridge)
Project Status:
Punch List
Bid Opening Date:
August 29, 2024 at 10:00 a.m.
Mandatory Pre Bid Meeting:
N/A
QuestCDN Number:
9267902
Construction Start Date:
October 7, 2024
Construction Completion Date:
December 2024
Contractor:
A Lamp Concrete Contractors, Inc.
Construction Engineer:
Edwin Hancock Engineering Company
Design Engineer:
Edwin Hancock Engineering Company
Awarded Contract Amount:
$698,174.75
Adjusted Final Contract Amount:
TBD
Funding Source(s):
Street Referendum

Objective

To improve the condition of the roadway by means of selected pavement rehabilitation methods. 

Description

This project consists of the rehabilitation of North Wisconsin Avenue from Vermont Street to Ridge Road by means of selected pavement rehabilitation methods.

Justification

The Village’s Pavement Management Program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.

Bidding & Planholders  Information

Bidding will be conducted online through the bidding service QuestCDN. More information will be posted when it becomes available.

Project Updates

Date
Description
December 13, 2024The only remaining site work is the completion of punch list items, which is ongoing.
December 6, 2024Final asphalt surface paving has been completed.
November 22, 2024The placement of longitudinal joint sealer was completed this week. Parkway restoration efforts, including placement of sod, were also completed this week. Final asphalt surface paving was anticipated to take place this past week, but was delayed due to weather. That paving is now expected to be completed next week, weather permitting.
November 15, 2024Paving of a preliminary layer of asphalt, or “binder course”, was completed this week. Parkway restoration efforts are now underway, with placement of sod expected to be completed by the middle of next week. Final asphalt surface paving will follow, weather permitting.
November 8, 204Milling and grading of the roadway and intersections t is nearly complete. Paving of a preliminary layer of asphalt, or “binder course”, is expected to take place early next week. It is recommended that residents park on side streets outside of the construction area during the workday to avoid any potential delays in getting vehicles out of driveways. Parkway restoration efforts will follow completion of the binder course, and final surface paving will follow parkway restoration.
November 1, 2024Construction of new concrete curb and gutter, driveway aprons, and sidewalk on the west side of Wisconsin is now complete. Most asphalt driveway aprons on both sides of Wisconsin are also complete, with only a few still remaining. Milling and grading of the roadway and intersections is expected to begin on Monday, November 4, 2024, weather permitting. 

To accommodate this work, there will be rolling closures of intersections next week. Weather permitting, Plymouth and Wisconsin will be closed on Monday, Sunset and Wisconsin on Tuesday, and Ridge and Wisconsin on Wednesday. If the weather delays work on one or more intersections then the actual days may change, but the order in which they are closed should remain the same. Daily detour routes will be posted for each closure. In addition to the intersection closures, the milling and grading operations will also impact motor vehicle traffic on Wisconsin between intersections. It is recommended that residents park on side streets outside of the construction area during the workday to avoid any potential delays in getting vehicles out of driveways.
October 18, 2024Construction of new concrete curb and gutter, driveway aprons, and sidewalk on the east side of Wisconsin was completed this week. Construction of asphalt driveway aprons on the east side will take place later in the project. Driveways on the east side are expected to be re-opened early next week, at which time construction efforts will move to the west side. Residents on the west side will be without driveway access while this work is taking place, beginning tentatively on Wednesday, October 23, 2024, and will be allowed to park on area streets overnight during this time. Residents on the west side will receive notice of the loss of driveway access in advance of the actual date by means of paper notices delivered to their doors.
October 11, 2024Removal of curb and gutter, driveway aprons, and sidewalk on the east side of Wisconsin began this week. Construction of new curb and gutter on the east side is expected to take place early next week, with construction of driveways and sidewalks to follow. After these efforts are completed on the east side, construction will move to the west side. Residents on the west side will be without driveway access while this work is taking place, and will be allowed to park on area streets overnight during this time. Residents on the west side will receive advanced notice of the loss of driveway access by means of paper notices delivered to their doors.
October 4, 2024Preliminary construction efforts, including underground utility locating, delivery of traffic control and materials, and sawcutting of the pavement, began this week. Full construction operations are expected to begin early next week.
September 27, 2024A pre-construction meeting was held this week. Construction is expected to begin the week of October 7, 2024. Preliminary construction efforts may begin sooner. Staff is currently working to coordinate pre-construction activities.
September 20, 2024Staff is in the process of executing contracts. Construction is expected to begin in early October.
September 13, 2024A contract was awarded this week for the Wisconsin Avenue Improvement Project (Vermont to Ridge). The contractor is A Lamp Concrete Contractors, Inc., of Schaumburg, IL. Staff is in the process of executing contracts.
September 6, 2024Staff is in the process of reviewing the bids and preparing a contract award recommendation. That recommendation is expected to be submitted at the September 9, 2024 Village Board meeting.
August 23, 2024The project has been advertised for bidding. A bid opening is scheduled for August 29, 2024.
August 9, 2024Design of the project is nearing completion.  Due to budgetary restrictions, the section from Ridge Road to Stone Road has been removed, and will be completed with a future project.
June 28, 2024An agreement for design engineering and construction engineering services for Wisconsin Avenue was approved at the June 24, 2024 Village Board meeting.
June 21, 2024A proposed agreement for design and construction engineering services for Wisconsin Avenue is being submitted for consideration at the June 24, 2024 Village Board meeting.
May 31, 2024Funding is available for further planning and design of the project.
January 1, 2024This project is still in the planning and concept stages. Further development of the project is precluded by available funding.
January 1, 2023
This project is still in the planning and concept stages. Further development of the project is precluded by available funding.
January 1, 2022
This project is still in the planning and concept stages. Further development of the project is precluded by available funding.
January 1, 2021This project is in the planning stages.